Project : Iowa Fertilizer Company
Project Type : Industrial
Location : Wever, Iowa
Project Description :

Largest Construction Project in Iowa History when announced to the public in November 2012.

Brief Listing of Quantities:
  1. 320 Acre Construction Site
  2. 1,200,000 CY of Earthmoving for site grading
  3. 180,000 CY foundation excavation cut
  4. 345,000 CY of foundation backfill
  5. 419,000 CY of topsoil stripping
  6. 88,000 LF Pipe of site water, sanitary sewer and storm sewer in our contract
  7. 500,000 tons of rock furnished & placed to date
http://www.mcaninchcorp.com/wp-content/uploads/2014/04/IowaFertPlant2-e1398794869811.jpg
http://www.mcaninchcorp.com/wp-content/uploads/2014/04/IowaFertPlant4-e1398456972899.jpg
http://www.mcaninchcorp.com/wp-content/uploads/2014/04/IowaFertPlant3-e1398794729374.jpg
http://www.mcaninchcorp.com/wp-content/uploads/2014/04/IowaFertPlant-e1398794660772.jpg