Branson Airport
Branson, MO

Construct a commercial airport from a "greenfield" site. grade and pave a 7400 LF runway, construct a 3.0 mile entranceway road with bridges, install water and sewer facilities, install fueling facility, construct parking lots and grade for a future terminal facility. Phase 1 Grading and storm sewers for new terminal site. Clearing - 27 Ac. Topsoil Strip - 240,000 cy. Unclassified Exc - 525,000 cy. Rock Exc - 58,580 cy. Respread - 81,500 cy. Erosion Control. Seeding, Trees, Landscaping. 94,588 sy Acc Paving and Rock Base. 11,354 lf Storm Sewer 15 "to 60". 858 lf Box Culverts 6'x3' to 10'x4'. Electrical Conduits - 29,800 lf. Light Pole Bases - 52

North Carolina 16
Lincoln/Catawba County, NC

For the North Carolina Department of Transportation, McAninch will move 5.1 million yards of earth and rock on the new alignment of NC 16. The $40.4-million project consists of 14 bridges, 4 box culverts, and 46,000 feet of storm sewer.

Route 36
Macon County, MO

For the Missouri Department of Transportation, McAninch will move 3.1 million yards of earth to upgrade Route 36 to a four lane divided highway. The $35.3-million project consist of 275,000 square yards of 12-inch concrete paving, 45,000 cubic yards of 8-inch un-bonded concrete overlay, 4 bridges, 3 box culverts, and 10,000 feet of storm sewer.

Route 60
Butler County, MO

For the Missouri Department of Transportation (MODOT), McAninch moved 3.0 million cubic yards, some of which was solid rock, for reconstruction of a 20-mile stretch of state highway near Poplar Bluff. The $34-million project involved 400,000 square yards of 12-inch concrete paving, three bridges, and ten box culverts.

 

Route 60
Carter County, MO

McAninch excavated 1.3 million cubic yards of earth and rock for this $15-million project. Structures included poured-in-place bridges, box culverts, roadway pipe, and 207,000 square yards of concrete paving.

 

Highway 5
Des Moines, IA

For the Iowa DOT, McAninch cut, filled, and graded four miles of four-lane right of way for the Highway 5 By-Pass east and south of Des Moines. On the $18-million project, 4.6 million cubic yards were moved in 14 months.

 

South Jordan Creek Parkway
West Des Moines, IA

McAninch is building a 1.4-mile South Jordan Creek Parkway for the City of West Des Moines. Earthmoving totals 720,000 cubic yards and 51,900 square yards of 10-inch PCC paving. McAninch underground crews will lay 10,250 linear feet of storm sewer pipe and 7,950 feet of water mains.

 

Des Moines International Airport
5,700-Foot Runway Extension

McAninch ran six excavators, 31 articulated dump trucks, and four D10/11 scrapers on two shifts for 130 days to cut and fill 5.2 million cubic yards and install 5,640 feet of storm sewer. Airport Engineer Bruce Rydberg reported: “McAninch provided the equipment and personnel to get the job done fast. They met the advanced deadline, saving a full construction season.”

Des Moines

6800 Lake Drive, Suite 125 • West Des Moines, IA 50266

phn 515-267-2500 • fax 515-267-2550

Kansas City

12980 Foster Street, Suite 150 • Overland Park, KS 66213

phn 913-685-8234 • fax 913-685-1140