Project Meta

McAninch provided site work and grading services for the Meta Data Center Campuses in Altoona, IA. Meta’s global infrastructure brings technologies and services to life, along with future immersive experiences like the metaverse — the next chapter of the internet. Altoona is the largest data center in Meta’s global fleet.  McAninch performed 100% the Civil scope of work, working with all trades on site. Work started June 14, 2013 and is expected to be completed June 2024.

Brief Listing of Quantities:

  • 12 Buildings Completed
  • 3,000,000 CY of Earth Moved
  • 750,000 Tons of Aggregate
  • 300,000 LF of Underground Utility Piping

Learn more about Altoona's Data Center by clicking here.